Schedule & Costs
GBT FEIP Proposed Project Schedule and Costs (Excluding Construction Cost Estimates)
This project is already underway and can be completed according to the current schedule if fully funded. The Schematic Design phase will likely be completed prior to the notification of award of TIGER grants, as will NEPA documentation, and the project will be in Design Development. This project is proposed to be “flash tracked” meaning, for example, the foundation package would be bid and construction started before the framing has been fully designed. This requires increased coordination between all members of the design team, construction management team, and the contractor(s). The schedule below details the current project phases and indicates substantial completion of the project by February 2012. Also detailed on the project schedule is the estimated funding draw-down by task.